MLT
REWS

Awtorizzazzjoni u Notifika għat-Tariffa Feed-In tal-PV's < 40 kWp

Last updated Nov 3, 2025

Applications to:

1. Request a Feed-in Tariff for a Photovoltaic Installation with capacity from 1kWp up to
less than 40kW;

  • Part 1 to be submitted through the One-Stop-Shop
  • Part 2 PV Operating Aid for applications not submitted through the One-Stop-Shop, and having been installed.

2. Request a Feed-in Tariff for a Photovoltaic Installation with capacity from 1kWp up to
less than 40kW;

3. Request a Change with Respect to an Existing Photovoltaic Installation

1.1: Application to Request a Feed-in Tariff for a Photovoltaic Installation from 1kWp up to less than 40kWp

The Regulator for Energy and Water Services administers the allocation and approval of feed-in tariffs for solar photovoltaic generation capacities in
accordance with the Feed-in Tariffs Scheme (Electricity Generated from Solar Photovoltaic Installations) Regulations (S.L. 545.27).

Any generating station must comply with the Electricity Regulations S.L. 545.34 which Regulations require that a generating station with a:

  1. rating equal or below 16 Amps per phase is to be notified to the Regulator for Energy and Water Services;
  2. rating exceeding 16 Amps per phase requires an Authorisation prior to its construction and a licence to generate electricity once such generating station is constructed.

Both the authorisation and the licence are issued by the Regulator for Energy and Water Services

Part 1

Any person wishing to install a solar photovoltaic installation and benefit from a feed-in tariff (FiT) is required to apply to the Regulator for Energy and Water Services before installing the PV installation. The application form required to be submitted through the One-Stop-Shop and selecting the FiT scheme, combines the request for the allocation of feed-in tariff and the application for an authorisation/notification process in terms of the Electricity Regulations S.L. 545.34.

In the case of eligible applications:

  1. for systems rated up to 16 Amps per phase or 20Amps per phase in the case where the inverter(s) is/are equipped with Volt-Var (see technical Note below) eligibility and the allocation of a FIT under the FIT scheme is confirmed through the issue the “ FiT confirmation letter” at the conclusion of the Part 1 PV application process
  2. for larger systems the applicant is guided through the One-Stop-Shop to first request a Preliminary Grid Study, based on the outcome of the preliminary grid study, the applicant may proceed with the submission of the Part 1 PV application through the One-Stop-Shop. Eligibility to the FiT scheme and the allocation of the FIT is confirmed by the issue of an “Authorisation to Construct” the PV installation. Note that the “Authorisation to Construct” is issued by the Regulator after the applicant complies with all requirements of the grid study and for the connection to the grid by the DSO (Enemalta Plc) and the DSO issues a “No Objection Letter”.

Part 2

Any person allocated a feed-in tariff through the Part 1 application process is required to submit the part 2 application to the Regulator for Energy and Water Services once the PV system is installed either through the Part 2 step in the One-Stop-Shop (where the Part 1 was submitted through the OneStop-Shop) or using the Part 2 Operating Aid (where the Part 1 application was not submitted through the One-Stop-Shop). This submission is necessary to:

  1. obtain a confirmation of the feed-in tariff allocated; and
  2. obtain a ‘Regulatory Clearance’; and
  3. obtain a licence to generate electricity for those installations issued with an “Authorisation to Construct”

Further information may also be found in a list of FAQ’s at: Multi generators configurations and FAQs.

Application to request a feed-in tariff and notify a solar photovoltaic installation or request an authorisation for a solar photovoltaic installation with a capacity ranging from 1kWp up to less than 40kWp as applicable:

Part 3

Applications submitted through the One-Stop-Shop, following the approval of the Part 2, need to proceed with the Part 3. The Part 3 step is necessary to apply with Enemalta plc to connect the PV to the grid and be provided with the necessary metering for the billing and payment of the FIT by ARMS Ltd.
In case of applications not submitted through the One-Stop-Shop, it is necessary to apply with Enemalta plc to connect the PV installation to the grid and be provided with the necessary metering for the billing and payment of the FIT by ARMS Ltd by submitting the ARMS Ltd PV Form together with the ‘Regulatory Clearance’ and licence (if applicable) issued by the REWS.

Technical Note
Guidance Notes on the Electricity Connection and Supply Regulations

The Electricity Connection and Supply Regulations (S.L.545.41)(ECSR) entered into force on the 29th October 2024 through legal notice 282 of 2024. These regulations replace the Electricity Supply Regulations (S.L.545.01). These regulations provide the terms and conditions for the connection of
loads, generators from renewable energy(RES), combined heat and power and storage to the electricity distribution grid up to the electricity service meter, metering, billing and electricity tariffs.

1.2: Application to Request a One-time Extension of the eligibility for a feed-in tariff of a Photovoltaic Installation (if applicable)

In terms of the Feed-in Tariffs Scheme (Electricity Generated from Solar Photovoltaic Installations) Regulations S.L. 545.27 , the allocation of a feed-in tariff by the Regulator for Energy and Water Services through the Part 1 Operating Aid process is valid for 12 months:

  1. for solar photovoltaic installations rated up to 16Amps per phase is valid for 12 months from the date of “FiT Confirmation” letter;
  2. for capacities exceeding 16Amps per phase is valid for 12 months from the date of Authorisation to construct the generating station and the date of issuance of the “Details to DSO” document

Notes:

  1. A one-time extension of the feed-in tariff allocation may be requested in case that the solar photovoltaic installation is not completed and an application to the DSO for connection to the grid is not submitted within such a stipulated time frame (12 months).
  2. Such a request for an extension has to be submitted to the Regulator and in such case the solar photovoltaic installation would be allocated the feed-in tariff available on the date of submission of the request for extension
  3. The extension would start from the day following the date of expiry of the first 12-month period irrespective of the date of request for an extension.
  4. In case the request for extension is accepted, the validity of the notification/authorisation, as applicable, will also be automatically extended

3. The extended period is 24 months for applications originally approved by a “FiT Confirmation” letter or a “Details to DSO” document before the year 2023, 12 months for those originally approved by a “FiT Confirmation” letter or a “Details to DSO” document from the 1st January 2023.

Any person wishing to request an extension of a feed-in tariff is required to apply to the Regulator for Energy and Water Services using the form PV FiT Extension.

Application Form:

1.3: Application to Request a Change with Respect to an Existing Photovoltaic Installation

A person who requires to make changes with respect to any existing PV system is required to submit an application in writing to the Regulator for Energy and Water Services. The Regulator for Energy and Water Services accepts the following applications for a change with respect to an existing PV installation:

  1. a change of the ownership (transfer of licence) of the solar photovoltaic installation;
  2. a change of the use of the premises;
  3. a change of the PV meter address or connection point (with or without the relocation of the solar photovoltaic installation);
  4. shifting of a PV from one meter to another meter to connect two existing PV installations together on the same meter (Shifting and Add-on).

The applicant is required to submit the following application to the Regulator for Energy and Water Services in the case of an application to request any of the above changes:

In addition to the above the following application forms should be submitted if the requested change consists in:

  1. A change of the ownership (transfer of licence) of the solar photovoltaic installation, the applicant is also required to submit the completed form entitled: Transfer of electricity generation licence.
  2. A change of the PV meter address or connection point (with or without the relocation of the solar photovoltaic installation), for a solar photovoltaic installation rated up to 16Amps, the applicant is also required to submit the completed form entitled: PV Notification Application form. v20
  3. A change of the PV meter address or connection point (with or without the relocation of the solar photovoltaic installation), for installations exceeding the 16 Amps per phase the applicant is also required to submit the completed form entitled: PV Authorisation Application. v28

2: Legal References

Feed-in Tariffs Scheme (Electricity Generated from Solar Photovoltaic Installations) Regulations S.L. 545.27
Electricity Regulations S.L. 545.34

3: Means of Authentication, Identification and Signature

  1. Details/number of the Identity card or passport or company registration number and/or the VAT number of the applicant as applicable.
  2. Details of the Identity card or passport or company registration number and/or the VAT number of the previous owner/previous licensee as applicable in case of a transfer.
  3. Details of the Identity card or passport number or company registration number and/or the VAT number of the new owner/new licensee as applicable in case of a transfer.
  4. Handwritten signature of the applicant (or all legal representatives in the case of a Company/Partnership) required on the application form.
  5. Handwritten signature of the previous owner/previous licensee (or all legal representatives in the case of a Company/Partnership) on the application form in case of a transfer.
  6. Handwritten signature of the new owner/new licensee (or all legal representatives in the case of a Company/Partnership) on the application form in case of a transfer.

4: Type of Evidence to be Submitted

Part 1 PV Operating Aid

  1. Copy/ Copies of the identity card/s or passport/s of the applicant or the Legal Representative/s in the case of a company / Legal Organisation;
  2. In case of a company or an organisation, a copy of an official Memorandum of Articles of Association for a company, or a copy of a Statute for an organisation indicating the President and the Secretary e.g. a Band Club or a copy of a VAT certificate if the applicant is a sole trader.
  3. In case that the installation is to be installed on a third party property, a copy of the identity card or passport of the site owner or occupier or the Legal Representative in the case of a company / Legal Organisation of the site owner or occupier, and this latter case a Memorandum of Articles of Association for a company or a copy of the Statute for an organisation indicating the President and the Secretary.
  4. Photos of the site proposed for the installation
  5. In case that the solar photovoltaic installation that are not roof mounted on an existing building, a Planning Authority permit, or a letter from the Planning Authority that a permit is not required.
  6. A copy of a recent electricity bill of the site proposed.
  7. Technical details of PV generator and a signed declaration by a warranted electrical engineer.
  8. In the case of a company or Legal organisation the details of the Legal Representative should be submitted.
  9. A signed declaration from the owner and/or occupier of the site where the PV installation is proposed confirming that there is no legal impediment for the installation and if the applicant is not the owner/occupier granting permission to the applicant to install the PV system on the site proposed. (included in item 4.2 of Part 1 Operating Aid).
  10. Estimated project costs (inclusive of VAT)
  11. Declaration regarding De Minimis State Aid received by the applicant in the current fiscal year(year in which the declaration is being submitted) until the date of the declaration in the application to benefit from a feed-in tariff and the de minimis aid received in the two previous fiscal years.

Part 2 PV Operating Aid

  1. Photos of the solar photovoltaic installation as installed;
  2. A dated purchase agreement or equivalent, signed by both PV supplier and applicant;
  3. A photo of the inverter(s) tally plate dated and signed in original by the warranted electrical engineer;
  4. A “No objection” letter issued by the DSO (Enemalta plc) for a PV installation with a rating exceeding 16 Amps per phase.

Request for an extension

  • In case of a PV system with a rating exceeding 1 6Amps per phase, a “No objection” letter issued by the DSO (Enemalta plc).

Request for transfer of ownership:

  1. In the case that the new owner is:
    1. a company, a copy of the official Memorandum of Articles of Association for such company is required to be submitted;
    2. an organisation, a copy of a Statute in the case of an organisation identifying the President and the Secretary e.g. a Band Club is required to be submitted;
    3. a sole trader, a copy of the VAT certificate is required to be submitted.
  2. In case of a PV installation with a rating exceeding 16 Amps per phase, a “No objection” letter issued by the DSO (Enemalta plc) for such transfer of ownership is also required to be submitted.

5: Applicable Fees

  1. No application fee applies for a PV installation with a rating less than 40kWp.
  2. No application fee applies for the request for extension or request for change to an existing PV installation.

6: Penalties and Offences

Regulation 59(1) of the Electricity Regulations (S.L.545.34) establishes that any person who contravenes any of the provisions of the Electricity Regulations or of a licence condition or of an authorisation or approval issued thereunder, shall be guilty of an offence, and shall, on conviction, be liable to a fine (multa) of not more than sixty-nine thousand euro (€69,000) or for one thousand and three hundred euro (€1,300) for each day during which the offence persists.
 
Regulation 59(2) of the Electricity Regulations (S.L.545.34) establishes that a person who, when information is requested or required by the Regulator, knowingly or negligently-

  1. gives any false, inaccurate or misleading information; or
  2. supplies incomplete information; or
  3. fails, without reasonable cause, to supply information requested within the time given; or
  4. prevents or hinders any investigation; or
  5. produces or furnishes, or causes or knowingly allows to be produced or furnished, any document or information which he knows to be false in any material respect,
  6. shall be guilty of an offence. and shall, on conviction, be liable to a fine (multa) of not less than one thousand euro (€1,000) and of not more than sixty thousand euro (€60,000) for each day during which the failure to comply subsists.

Regulation 59(3) of the Electricity Regulations (S.L.545.34) establishes that where any person fails to comply with the provisions of the regulations or of a licence or authorisation condition for a period not exceeding three months, the Regulator may revoke such licence or authorisation.
 
Regulation 60(1) and 60 (2) of the Electricity Regulations (S.L.545.34) establish that the Regulator may impose an administrative fine upon any person who infringes any provision of the regulations or who fails to comply with any directive or decision given by the Regulator in ensuring compliance with these regulations and such fines:

  1. shall not exceed one hundred thousand euro (€100,000) for each contravention and, or six hundred euro (€600) for each day of noncompliance, from the date of the decision given by the Regulator; and
  2. in the case of an undertaking (including a vertically integrated undertaking) or a body corporate, up to 10%   of the total turnover concerned in the preceding business year. Provided that in the case of an undertaking, including a vertically integrated undertaking or a body corporate, a fine of up to 10% of the annual turnover concerned in the preceding business year, even if such fine results in an amount that exceeds the one hundred thousand euro (€100,000) threshold may, in any such case be imposed.

7: Deadlines or Indicative Time that the Regulator Requires to Complete the Procedure

No specific period for completion of the procedure is established at law.

Generally, applications are processed within 10 days provided that no clarifications and/or site inspection are required.

The Regulator for Energy and Water Services publishes a list of applications for a feed-in tariff submitted to it and their respective status, on the Regulator’s website and this list is updated periodically. Applicants may refer to the following link: PV Capping Status.

8: Rules on Lack of Reply from the Regulator and Legal Consequences

In general, the Maltese Administrative Law establishes that in the absence of a reply this is construed to be tantamount to a refusal and the applicant has a right to appeal.

9: Means of Redress of Appeal

In case of refusal of the allocation of a feed-in tariff (Part 1 stage) or non-confirmation of the feed-in tariff (Part 2 stage) the applicant may apply for the review of the refusal to the Feed-in tariff Evaluation Committee within 20 days from the date of the letter of refusal

Any decision taken by the Regulator, including refusal of an application for or withdrawal of an authorisation or a licence, may be subject to appeal before the Administrative Review Tribunal established by Article 5 of the Administrative Justice Act.

10: Competent Authority

You may submit the application form together with all associated documentation and relevant payments referred to in the application form either by post or by hand to:  
Regulator for Energy and Water Services,
Zentrum Business Centre, Level 1,
Mdina Road,
Qormi, QRM 9010,
Malta.